MassDOT Design-Build Projects
|
||
|
Procurement Schedules as of 5/4/20
|
||
|
Project/ Office Estimate
|
Adv. Date (RFP)
|
Projected NTP
|
|
Southborough/ $48M
|
2/29/2020
|
8/19/2020
|
|
Newton-Weston / $160M
|
11/1/2020
|
5/1/2021
|
|
Hopkinton / $290M
|
6/1/2021
|
12/1/2021
|
|
Davol Street/ $82M
|
10/1/2021
|
3/1/2022
|
|
Allston/$700M
|
2/1/2022
|
10/1/2022
|
|
Charlton-Oxford/$62M
|
2/1/2022
|
7/1/2022
|
|
Haverhill (South)/ $80M
|
4/1/2023
|